Project lifecycle reporting - pending approvalSubmitted by Catherine L from Ministry of Transport on Tue, 2008-09-02 15:08.
Hi, Can you tell me if it is possible to report against the project lifecycle status, where the approval is PENDING? Cheers |


Hi Catherine We currently do
Hi Catherine
We currently do not have a report that shows where a life-cycle change is ‘pending’. This life-cycle change assessment will of course appear on the work-owned tab of the home page of the approver.
I understand your requirement to be able to see outstanding project approvals. We will discuss how we can best address this requirement at our management meeting next week and will then post a response.
New report
Hi Catherine
we will develop a report that identifies outstanding items across a range of areas including items such as decisions and change requests as well as life-cycle change approvals.
Thanks Paul. Sounds great -
Thanks Paul.
Sounds great - will be a real help for us!