Is an issue automatically created when a calendar change takes place?

Issues are created if the calendar change affects the project end date.

How does i-lign calculate task end dates?

First there are the pre-requisites followed by the calendar definition for the project.

How do I set-up public holidays for everyone?

Holidays can be defined for all staff through the organisation's base calendars. Each staff member is assigned a base calendar when they are created as a resource in i-lign.