Subject category: Allocations
News feed for this listing: Syndicate content

Resource allocations for BAU activities

Overhead tasks can be used to allocate a percentage of a resource's time against BAU activities for a specified time period.

Can I allocate a resource against a single task with multiple allocation rates?

This can be achieved in i-lign using a task pool, but is not possible in i-lign for standard tasks, where only one allocation rate can be set per resource per task.

How does i-lign calculate task end dates?

First there are the pre-requisites followed by the calendar definition for the project.