Resource allocations for BAU activities

Overhead tasks can be used to allocate a percentage of a resource's time against BAU activities for a specified time period.

Can I allocate a resource against a single task with multiple allocation rates?

This can be achieved in i-lign using a task pool, but is not possible in i-lign for standard tasks, where only one allocation rate can be set per resource per task.

How does i-lign calculate task end dates?

The first factor i-lign uses in determining task end dates is the length of the working day.