Topics from the 'Program Managers' and 'Project Managers' categories:
PDF Reports - Risk Trend Graphs
Project risks can be displayed as graphs mapping the risk score over time. Last edited by Elaine on Fri, 2007-09-07 09:35.
How do I apply a mitigating action against a risk?
A mitigation strategy comprising of Preventative and Contingent actions can be created against a risk only after the original risk has been created and saved. This applies to both Project and Portfolio risks. Last edited by Bryn from i-lign on Mon, 2007-09-10 17:06.
Can the risk likelihood and consequence scales be changed?
Risk likelihood and consequence numeric scales are hard-coded into i-lign and cannot be modified. However, from v3.2 onwards, their descriptive terms can be customised to align with an organisation's individual risk management strategy. Last edited by Elaine on Wed, 2007-06-06 09:25.
Project Budget Totals
The Project Budget displays monthly budgeted and actual financial information for one financial year at a time. Last edited by Elaine on Tue, 2007-02-27 11:53.
Can a risk be assigned to more than one project?
An individual risk cannot be assigned to more than one project other than by assigning it to the projects' parent porfolio. Last edited by Elaine on Tue, 2007-03-20 13:08.
Managing project number allocation
Project number allocation can be centrally managed either externally to i-lign or by using i-lign's auto-number generation function. Last edited by Elaine on Tue, 2007-03-20 16:05.
It's the end of the financial year, how do I separate financial and project data between years?
When i-lign was implemented at your organisation, financial years were set up. You can view the list, and the start/end dates for each year, on the Financial Years page. Last edited by Elaine on Tue, 2007-03-20 17:28.
End dates and display defaults
Resources, goals, strategies, teams and portfolios all have an end date assigned to them. Last edited by Elaine on Tue, 2007-03-20 15:03.
Can I change the date of a cross-project dependency?
No, the dependent task cannot be changed by your project. Last edited by Elaine on Tue, 2007-03-20 15:09.
|
||||||||||||||||||||||||||||||||||||||||||||||||||